SUMMARY

Able completed a Time & Materials project in which they provided labor, supervision, equipment, and materials necessary to execute the Olefins 1 Turnaround for Ineos O&P. Able successfully competed all compliance driven scope, maintenance repairs and capital projects. The general scope included blinding and opening towers, exchangers, and vessels for inspection. Removing control valves and sending them for repairs, replace valves in kind. Demo, fit, and weld piping. Blind and de-blind systems and battery limits for maintenance and install unit clearing piping and tie-ins for chem cleaning. Able also provided Planning, Scheduling, and TAR Execution readiness services to prepare for the event.

FEATURES

Location

INEOS Chocolate Bayou – 15926 FM 2004, Alvin, TX 77511

Client

INEOS Olefins & Polymers

Total Project Manhours

137,366

Safety Stats

0 Recordables, 0 First Aids, 1 Near Miss

Quantities of material installed

  • Number of flanges Make-ups – 2,511
  • Number of welds made – 837
  • Repair rate – 0012%
  • Material Welded – CS, CS-LT, 304SS, 316SS, 309SS, 1 ¼ Chrome, 2 ¼ Chrome
  • LF of Pipe Fabricated / Installed – 2,360
  • Equipment Worked on
    • Exchangers – 54
    • Towers – 5
    • Drums – 26
    • Welded Piping – 119
    • Bolted Piping – 79
    • Valves – 103
    • Cold box – 1