220299 T-209 Tower & U-33 1500LB Steam Header

SUMMARY

Full replacement of T-209 tower. Demo and reuse piping. Fabricate 10” 1500 lb steam header, demo and replace. Built crane pad and laydown yard for tower. 

FEATURES

Location

Sweeny, TX

Client

Chevron

Total Project Manhours

21,486

Quantities of material installed

  • Welds Made: 261
  • CS Pipe
  • SS Pipe
  • 2 ¼ Chrome
  • Bolt Ups: 81
  • 786 ft of pipe
  • Est. 100 Tons of Steel
  • Est. 900 Tons of crushed concrete
  • Est. 200 Tons of 1” rock